When producing the site specifications requirements report for a routing and switching solution, which two tasks are performed prior to producing a customer site survey report? (Choose two.)
A.
Survey all environmental and physical details of specified sites.
B.
Produce site requirements specifications that assess and document the physical, electrical, and environmental
specifications.
C.
Develop the site survey report that details site information such as physical, environmental considerations, AC/DC electrical supplies, cabling, network synchronization, peripheral equipment, and remote access.
D.
List all networking and applications devices to be implemented.
E.
Gather existing system and site documentation.