Which statement about migrating to Cisco Unified Communications is true?

Which statement about migrating to Cisco Unified Communications is true?

Which statement about migrating to Cisco Unified Communications is true?

A.
A phased migration is best suited for single-site deployments, whereas a parallel cutover is better for multisite deployments.

B.
If something unexpected occurs, the phased migration provides a back-out plan that allows you to revert, with minimal effort, to the previous system, which is essentially still intact.

C.
A phased migration allows you to revert, with minimal effort, to the previous system.

D.
A phased migration purchases individual components of the system as and when they are needed.