When a meeting is planned to obtain design approval for a legacy system interface, a representative of which of
the following parties must be in attendance?
A.
End-users
B.
Project Manager
C.
Project sponsor
D.
Information systems
Explanation:
Note: If only one then the answer would be “C.”