what happens when new requirements are added to the solution if there are no controls in place?

Once the customer has signed off on the formal requirements documentation, what happens when new
requirements are added to the solution if there are no controls in place?

Once the customer has signed off on the formal requirements documentation, what happens when new
requirements are added to the solution if there are no controls in place?

A.
Requirements creep

B.
Requirements renewal

C.
Requirements expansion

D.
Requirements re-gathering

Explanation:
Requirements creep is a tendency for product or project requirements toincrease during development beyond

those originally foreseen, leading to features that weren’t originally planned and resulting risk to product quality
or schedule.