What is the next step?

During the implementation phase of an Electronic Document Management System (EDMS)
project, the Project Manager discovers that the storage system will not arrive by its targeted
installation date. What is the next step?

During the implementation phase of an Electronic Document Management System (EDMS)
project, the Project Manager discovers that the storage system will not arrive by its targeted
installation date. What is the next step?

A.
Create a project change request and submit it to the project committee

B.
Change the project Gantt chart to reflect the new expected date

C.
Order a storage system from another vendor

D.
Proceed as normal because the project schedule will resolve itself



Leave a Reply 0

Your email address will not be published. Required fields are marked *