In an attempt to ease cultural change anxiety, the Project Manager speaks to end-users and
managers. All of the following should be addressed EXCEPT the:
A.
integration of the Document Management System (DMS) with existing applications.
B.
benefits that the new system will have on the end-users job.
C.
training that will make the end-user more valuable.
D.
number of jobs that will be reduced through the efficient use of technology.