A system implementation is complete when which of the following has occurred?
A.
All users have been trained and are able to use the system.
B.
All system components have been installed and the system runs well.
C.
The system administrators have reviewed the system and accepted responsibility for it.
D.
The completion standards defined in the agreement have been met and the system performs as
described.