During the project planning phase, it is essential for the consultant to obtain which one of the
following?
A.
A Gantt chart with all of the correct resources on the project
B.
A work breakdown structure with all of the tasks required
C.
A cultural change document with steps to ensure a smooth transition
D.
Documentation of the clients acceptance for each part of the project