A finance company receives 10,000 documents per week. 40% of the documents arrive on Tuesday
morning. The customer has a five-day work week with seven-hour workdays. Their office space can
accommodate only one scanner. What is the minimum effective throughput required for the scanner
in order to handle the volume?
A.
6 pages per minute (ppm)
B.
10 ppm
C.
18 ppm
D.
22 ppm