An existing capability is being migrated into the cloud. Capacity management issues have been
noticed in the past and an exercise is being performed to calculate current and future volumes. In
which of the following lifecycle phases is this likely to be performed?

An existing capability is being migrated into the cloud. Capacity management issues have been
noticed in the past and an exercise is being performed to calculate current and future volumes. In
which of the following lifecycle phases is this likely to be performed?

A.
Operation

B.
Design

C.
Transition

D.
Strategy