For budget purposes, the accounting department has asked an administrator to provide a disaster recovery solution that will comply with the following requirements:
– Systems have to be operational within two days
– No disaster will be declared if the primary site is fully operational within 24 hours
Which of the following is the BEST solution the administrator can propose to the accounting department?
A.
Warm site
B.
Cold site
C.
Hot site
D.
Mirrored site
C.