Which of the following would be the LAST area to shut down?

A company is implementing a private cloud infrastructure and is testing its high availability components. In a planned outage test, all systems will be shut down sequentially. Which of the following would be the LAST area to shut down?

A company is implementing a private cloud infrastructure and is testing its high availability components. In a planned outage test, all systems will be shut down sequentially. Which of the following would be the LAST area to shut down?

A.
Offsite mirror

B.
Networking

C.
Hypervisors

D.
Storage



Leave a Reply 1

Your email address will not be published. Required fields are marked *