A Chief Information Officer (CIO) has summoned an administrator due to the datacenter power bill being significantly higher than normal. The administrator explains that a new array was installed for a 20TB CRM application. Which of the following solutions would provide a new performance benefit and also reduce power consumption?

A Chief Information Officer (CIO) has summoned an administrator due to the datacenter power bill being significantly higher than normal. The administrator explains that a new array was installed for a 20TB CRM application. Which of the following solutions would provide a new performance benefit and also reduce power consumption?

A.
SSD

B.
SAS

C.
SATA

D.
FC