Engineers are preparing to move guests to new compute and storage infrastructure. Basic network and SAN connectivity have been established. Which of the following options are valid NEXT steps to prepare for guest migration to the new infrastructure? (Select TWO)
A.
Tag the live migration VLAN on the trunk to the new servers
B.
Correctly size and provision NFS LUNs on the new storage
C.
Zone HBAs
D.
Prep mirror VMs on new hosts for data migration
E.
Tag the SAN trunks with the correct guest network VLANs
The aiotestking admin posted the latest version (July 24, 2017) of CompTIA Cloud+ CV0-001 (v.1) exam questions. The technology world is converting into the Cloud technology. Let’s try to resolve these questions and pass this exam.
http://www.aiotestking.com/comptia/category/quiz-cv0-001/
A and D are correct