Select the true statement regarding Portfolio Scenarios.

Select the true statement regarding Portfolio Scenarios.

Select the true statement regarding Portfolio Scenarios.

A.
You can add user access to the Portfolio Scenario from waterline analysis.

B.
You can save the Waterline Analysis as a new scenario.

C.
You can update individual project status from the Waterline Analysis/Scenario.

D.
You can create a new portfolio from the Waterline Analysis.

Explanation:
Use the Capacity Planning page to perform What-if analysis, graphically change
project forecast dates, and apply waterline analysis techniques to assist with critical, executivelevel decision making. Before assessing capacity or demand on resources, create resource and
role estimates for each project. During your analysis, you can create and update scenarios that
provide varying snapshots of project and role allocation data. After conducting your analysis, you
can create new portfolios containing only the projects that meet your planning criteria (D).

Note: Create Portfolio Scenarios to capture Portfolio data for comparisons and analysis.
Create Portfolio Scenarios to capture Portfolio data for comparisons and analysis
Reference; P6 EPPM User’s Guide,About Capacity Planning