Which Percent Complete Type would be the best selection for activities in this project?

You are a Project Manager whose projects are integrated with Financial Management System
(FMS). The FMS pushes Actual Costs and Actual Hours to your projects as of the Actual Date.
Updating Percent complete using the pushed Actual Dates, Actual Costs, and Actual Hours has
created inaccurate pictures of the overall % complete, because there are steps within activities
that clearly have not completed.
Which Percent Complete Type would be the best selection for activities in this project?

You are a Project Manager whose projects are integrated with Financial Management System
(FMS). The FMS pushes Actual Costs and Actual Hours to your projects as of the Actual Date.
Updating Percent complete using the pushed Actual Dates, Actual Costs, and Actual Hours has
created inaccurate pictures of the overall % complete, because there are steps within activities
that clearly have not completed.
Which Percent Complete Type would be the best selection for activities in this project?

A.
Physical

B.
Units

C.
Effort

D.
Duration

Explanation:
Use physical to give a selection corresponding to the actual state.
Note: Parameter: Percent Complete Type
* Identifier: p_percent_complete_type
* Details: Allows users to select the percent complete type of an activity.
* Values: Physical, Duration, Units
* Maps to field: ACTIVITY.PERCENTCOMPLETETYPE
* Use case: Filter activities in a report based on the percent complete type of the activity.
Note 2: There are many different methods for calculation of actual progress in Primavera P6.
These methods involve using many fields and settings, including:
Duration % Complete
Units % Complete
Physical % Complete
Percent Complete Type
Activity % Complete
Performance % Complete
Earned Value settings of the WBS Elements