An activity is to be completed within a fixed time period and the total amount of work is fixed. What
duration type should be used?
A.
Fixed Units
B.
Fixed Duration and Units/Time
C.
Fixed Units/Time
D.
Fixed Duration & Units
Explanation:
For Fixed Duration & Units, the duration and units remain constant as the units/time
are changed. Use this duration type when the activity must be completed within a fixed time period
and the total amount of work is fixed.
Note: Duration TypeDuration type determines how remaining duration, units, and units/time will be
calculated when you update an activity that has resources assigned. The activity’s duration type
should correspond to the factor that is least flexible in the project: schedule, costs/work effort, or
resource availability.