You can create a Calculated User Defined Field for which Subject Area?
A.
Activity
B.
Resource
C.
Project
D.
Security
Explanation:
Defining Formulas for User Defined Fields
Define formulas to calculate values for the user defined field.
Before defining a formula, you need to first create a project user defined field
To define formulas for user defined fields:
1) Click the Projects menu and select Enterprise Project Data, or click the Administer menu and
select Enterprise Data.
2) In the Enterprise Data pane, expand Projects and click Project UDFs.
3) On the Project UDFs page, select a UDF and click the Formula detail window.
Note: The UDF Type must be set to Formula to access the Formula detail window.
4) In the Formula detail window:
a. Click the Fields list and choose a field.
Note: You can select any existing project-related field defined in the project management
database, including project codes, or any other user defined field that exists for your organization.
b. Click Insert Field.
c. Continue to build your formula by inserting fields and using the operator buttons.
5) Click Save (Ctrl+S).Reference; P6 EPPM User’s Guide, Defining Formulas for User Defined Fields