What is the significance of the setting "Summarize project based on detailed activity resource assignments"?

What is the significance of the setting “Summarize project based on detailed activity resource
assignments”?

What is the significance of the setting “Summarize project based on detailed activity resource
assignments”?

A.
Summarized project data will reflect Top Down plans.

B.
Summarized project data will reflect Bottom Up plans.

C.
Summarized project data will reflect integrated Actuals.

D.
Summarized project data will be monetized.

Explanation:
Use the Detail Activity Resource Assignments option for in-progress projects when
you want to review detailed activity-level summarized data, for example, for earned value
reporting.
Note: You can specify several default values that will be used for activities when you create new
projects.
One such setting is ‘Summarize Project Based on’.
‘Summarize Project Based on’ determines whether the Summarizer calculates and displays rolledup data based on resource assignments at the activity or project level.
Reference: Set Project Default Options
http://docs.oracle.com/cd/E17462_01/Web_Access/Help/en/Projects/Tasks/pm_p_setdefaults.htm