When viewing the Resource Usage Profile using the date interval of Week/Day1, resource
allocation is being displayed only on Sundays for every resource being analyzed.
Why are all of the resource allocations being displayed on the same day of the week rather than
across the days when they are scheduled to occur?
A.
All resources are assigned to the project’s default calendar, and have been over allocated to
other projects.
B.
The resource calendar assigned to the resources was deleted by the System Administrator.
C.
On the General tab. In the Admin Preferences dialog box, the first day of the week field is set to
Sunday.
D.
On the Resource Analysis tab, in the User Preferences dialog box, the “Interval for timedistributed resources calculations” field is set to “week.”
it should be option D