Identify the key benefit of Plan Resources View.

Identify the key benefit of Plan Resources View.

Identify the key benefit of Plan Resources View.

A.
You can create scenarios using waterline analysis.

B.
You can identify staffing shortfalls within detailed project plans.

C.
You can view and analyze resource allocation without assigning resources at the activity level

D.
You can view and assign resources mapped to appropriate Roles with highest skills.

Explanation:
Note: You can delete a financial period that has high-level assignment planning values (as entered
on the Plan Resources page of P6) as long as the financial period does not contain past period
actuals. When you delete a financial period that has high-level assignment planning values, the
values are deleted as well.