The Total Spending Plan Tally for a project is the sum of the Spending Plans assigned to____.
A.
each project in the Enterprise Project Structure (EPS)
B.
each Work Breakdown Structure (WBS) element in the project
C.
each immediate child Work Breakdown Structure (WBS) element
D.
each immediate parent Work Breakdown Structure (WBS) element
Explanation:
Total Spending Plan Tally applies to each project.
Note: Enter monthly spending amounts at the EPS level
Click the Spending Plan tab in the Projects window for a selected EPS node or project. Enter total
expenditures for each month in the Spending Plan column. The Spending Plan Tally column
shows any amounts previously recorded for project spending plans.
Reference; Oracle Primavera P6 Project Management, Reference Manual, Enter monthly
spending amounts at the EPS level