Weighted Project codes______.

Weighted Project codes______.

Weighted Project codes______.

A.
are rarely used due to maintenance issues

B.
are used to calculate Project Score

C.
are used at the Activity level

D.
are assigned by the System Administrator

Explanation:
Primavera uses the weighted project code and code values assigned to a project to
calculate its score. To use project scoring features, you create weighted project codes that
represent project criteria you want to evaluate, for example, projected sales and risk. You further
express the possible attributes associated with these evaluation criteria as weighted project code
values, for example, projected sales might be described as either high, medium, or low potential.
Finally, you assign the appropriate weighted codes and code values to the projects you want to
score.
Reference: Project Scoring Process Overview