You are a Project Manager who is closing out a completed project. You have confirmed that all
hours that should be charged to the project have in fact been charged. You have conducted your
Lesson Learned activity. All parties agree that the project is complete.
Which project status is the best choice for this project?
A.
Active
B.
Inactive
C.
What-If
D.
Planned
Explanation:
The InactiveProject Status should be given to projects that have been completed
or curtailed so there will be no more work left to do on them.
Note: The P6 Project Status field is found on the General tab of a Primavera P6 project whether
you are using P6 Professional or P6 web.
It can be set to one of four values; Planned, Active, What-If or Inactive.