Select the true statement regarding Global Change.

Select the true statement regarding Global Change.

Select the true statement regarding Global Change.

A.
Global change can be executed by any user.

B.
Global change can modify Global Codes.

C.
Global change can modify Global Security Profiles.

D.
Global Change can replace existing project data with new data.

Explanation:
primavera p6 Global change feature enables you to make changes to all activities,
or a selected group of activities, at one time. You can use Global change to edit existing values or
assign new values. For example, you can create a statement to assign resource assignments to a
group of activities.
When you run Global change, data exclusively locked by another user does not change. To obtain
exclusive access, before opening the project, choose Exclusive in the Access Mode section of the
Open Project dialog box.
You must have access to the activities to which you want to make Global changes. If your security

profile does not enable you to access all the activities, you will not be able to commit the changes
you make.
Global change conditions
If statements control which project data changes. Then and Else statements specify the changes
to be made. You can define an unlimited number of If, Then, or Else statements.
Reference: Primavera P6 Global Change