Cost accounts are hierarchical, and______.

Cost accounts are hierarchical, and______.

Cost accounts are hierarchical, and______.

A.
are assigned in Project Details

B.
are created and managed at the Project level

C.
are applicable to all projects in the EPS

D.
are assigned to users with security

Explanation:
In primavera P6 we can create cost accounts and associate them with activity
resource assignments or expenses in a project. Cost accounts are hierarchical, and they enable
you to track activity costs and earned value according to your organization’s specific cost account
codes.
You can specify a project’s default cost account. This cost account is used for resource
assignments to activities and project expenses in the open project.
Note: You can specify a project’s default cost account. This cost account will be used for resource
assignments to activities and project expenses in the open project.
Reference: Oracle Primavera P6 Cost Account