Select two true statements regarding Calendars.
A.
Global Calendars are available to a subset of projects.
B.
Project Calendars are available for the current project only.
C.
Only a limited number of calendars can be created.
D.
Resource calendars are applied to all Resources with the same Primary Role.
E.
Activity type determines whether the activity uses Resource Calendars for scheduling.
F.
Activity Calendars are managed by individual Resources.
b & e