which of the following NEXT?

A system experiences a fatal crash and the programmer must make an immediate change to fix it.
Best practice dictates the programmer should do which of the following NEXT?

A system experiences a fatal crash and the programmer must make an immediate change to fix it.
Best practice dictates the programmer should do which of the following NEXT?

A.
Remove the change after the system comes back up.

B.
Contact the vendor to provide an official patch.

C.
Follow up on another solution at the next change control meeting.

D.
Fill out an emergency change control statement.