Select the best definition of Resource within Primavera P6 EPPM.

Select the best definition of Resource within Primavera P6 EPPM.

Select the best definition of Resource within Primavera P6 EPPM.

A.
Labor effort required to complete an activity

B.
Materials used to complete an activity

C.
Anything used to complete an activity

D.
Equipment required to complete an activity

Explanation:
Estimating Activity Resources is “the process of estimating the type and quantities
of material, people, equipment, or supplies to perform each activity.”
If the contract documents require resource and/or cost loading, the
Scheduler must assign resources to the activities. Even if the contract does not require resource /
cost loading, it is
good practice; “by assigning (i.e. loading) resources for each activity, available resources can be
scheduled in
accordance with resource consumption limitations (i.e., money, labor hours, etc) by resource
leveling or balancing”
Reference: Project Management Institute. Chapter 6: Project Time Management. A
Guide to the Project Management Body of Knowledge (PMBOK ®), Fourth
Edition. Page(s) 129-164. Project Management Institute, Newton Square,
PA. 2008.



Leave a Reply 0

Your email address will not be published. Required fields are marked *