Which action should be executed in the Client?

You are working in a project plan that has been baselined multiple times. Each of the baselined
reflects expected effort for three different sets of defined scope. After reviewing the plan,
management has decided that a previous baseline/scope definition will be used going forward.
Which action should be executed in the Client?

You are working in a project plan that has been baselined multiple times. Each of the baselined
reflects expected effort for three different sets of defined scope. After reviewing the plan,
management has decided that a previous baseline/scope definition will be used going forward.
Which action should be executed in the Client?

A.
Restore

B.
Copy/Paste

C.
Export

D.
Check Out

Explanation:
Restore a Baseline: Use restore a baseline to modify a baseline project. You must
first unlink a baseline from its current project by restoring it as a separate project. You can then
work with this restored baseline project as you would any other project in the EPS.
Reference; P6 EPPM User’s Guide, Working with Baselines