Which project status is the best choice for this project?

You are a Project Manager working on a new project. You have just received the Project Scope of
document that has provided a top-down timelines and budgets for the project. The project has not
started. Which project status is the best choice for this project?

You are a Project Manager working on a new project. You have just received the Project Scope of
document that has provided a top-down timelines and budgets for the project. The project has not
started. Which project status is the best choice for this project?

A.
Active

B.
Inactive

C.
What-If

D.
Planned

Explanation:
A Planned Project Status should be assigned to a P6 Project that is currently being
developed into a project that should start in the future. Of course some of the best planned
projects don’t ever start.
Note: The P6 Project Status field is found on the General tab of a Primavera P6 project whether
you are using P6 Professional or P6 web.
It can be set to one of four values; Planned, Active, What-If or Inactive.