Select the true statement regarding summarized data and Primavera Web.
A.
Live data is used for Resource management.
B.
Live data is used for Portfolio management.
C.
Summarized data is used for Resource management.
D.
Summarized data is used for Project management.
Explanation:
The Project Baseline is a single metric for comparison that enables all members of a
team to have a shared and consistent set of data against which to evaluate project progress.
There is only one Project Baseline at any time. All pages that display summarized data compare
and display data against the Project Baseline.
Reference; P6 EPPM User’s Guide, About Baselines