You are a Portfolio Manager with one project that is clearly underperforming. You would like to
obtain more information about where the problems in the project reside. How would you do this in
Primavera P6 EPPM Web interface without contacting the Project Manager?
A.
Click the project name to view performance data by Work Breakdown Structure (WBS).
B.
Send an email asking for more information from the Project Manager.
C.
Send an alert via workflow asking for more information from the Project Manager.
D.
Create an Issue for follow-up by the Project Manager.