Identify three best practice uses of Notebook topics.
A.
Document processes.
B.
Explain a Constraint.
C.
Send out an email alert.
D.
Explain baseline update.
E.
Change User Access.
F.
Update Actual Costs.
G.
Provide additional status information
Explanation:
1) Always add a Notebook topic once a constraint is added.
2) You can add two constraints per activity
3) Always reschedule your project after adding a constraint to calculate the new dates.
Note 1:
To assign a constraint to an activity, you can go to the Activity Window and select the Status tab
in the Activity details.
Types of Constraints;
1) Start on
2) Finish On
3) Start on or After
4) Start on or Before
5) Finish on or After
6) Finish on or Before
7) As Late as possible
8) Mandatory Start and Finish.
Note 2: Constraints are used to reflect real project scenarios like your Document submission date,
Awarding of Contract…etc. Primavera’s scheduled date might not be the one which is in reality, so
that’s where when assigning a constraint comes in to the picture.
This is assigned to place an overall deadline for your project. Your project
Constraints are used to reflect real project scenarios like your Document submission date,
Awarding of Contract…etc. Primavera’s scheduled date might not be the one which is in reality, so
that’s where when assigning a constraint comes in to the picture.