The data center will be powered off for several hours. In order to make the date center continue working, which action will be taken first?
A.
Connect all the switches to a generator.
B.
Connect all the switches to a battery backup.
C.
Connect the data centers power to a generator.
D.
Connect the data centers power to a UPS.