Which of the following documents should be referenced?

A project team member is uncertain how many activities are required to complete a task. Which of
the following documents should be referenced?

A project team member is uncertain how many activities are required to complete a task. Which of
the following documents should be referenced?

A.
Key Performance Indicators (KPIs)

B.
Project charter

C.
Work Breakdown Structure (WBS)

D.
Statement of Work (SOW)

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *