Which of the following is created using the work breakdown structure (WBS) as an input?

Which of the following is created using the work breakdown structure (WBS) as an input?

Which of the following is created using the work breakdown structure (WBS) as an input?

A.
Procurement management plan

B.
Vendor selection criteria

C.
Project scope statement

D.
Project charter

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *