A project manager has decided to increase the number of resources working on critical path
activities. This is an example of:
A.
rolling wave planning.
B.
resource leveling.
C.
fast tracking.
D.
crashing.
Explanation:
A project manager has decided to increase the number of resources working on critical path
activities. This is an example of:
A project manager has decided to increase the number of resources working on critical path
activities. This is an example of:
A.
rolling wave planning.
B.
resource leveling.
C.
fast tracking.
D.
crashing.
Explanation: