Which of the following are created using information contained in the work breakdown structure (WBS)?

Which of the following are created using information contained in the work breakdown structure
(WBS)? (Select Two).

Which of the following are created using information contained in the work breakdown structure
(WBS)? (Select Two).

A.
Project scope statement

B.
Project statement of work

C.
Project charter

D.
Project activity estimates

E.
Project resource estimates

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *