Which of the following represents the appropriate order of an effective change management process?

Which of the following represents the appropriate order of an effective change management
process?

Which of the following represents the appropriate order of an effective change management
process?

A.
Identify change, perform impact analysis, approve or deny change, update applicable project
plan components, document change.

B.
Identify change, document change, perform impact analysis, approve or deny change, update
applicable project plan components.

C.
Identify change, document change, perform impact analysis, update applicable project plan
components, approve or deny change.

D.
Identify change, document change, approve or deny change, perform impact analysis, update
applicable project plan components.

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *