Which of the following cost estimating techniques uses previous, similar projects as a basis of estimating costs for the current project?

Which of the following cost estimating techniques uses previous, similar projects as a basis of
estimating costs for the current project?

Which of the following cost estimating techniques uses previous, similar projects as a basis of
estimating costs for the current project?

A.
Top-down estimating

B.
Parametric estimating

C.
Bottom-up estimating

D.
Analogous estimating

Explanation:



Leave a Reply 0

Your email address will not be published. Required fields are marked *