which of the following process groups is the preliminary project risk assessment performed?

During which of the following process groups is the preliminary project risk assessment
performed?

During which of the following process groups is the preliminary project risk assessment
performed?

A.
Monitoring/Controlling

B.
Planning

C.
Initiating

D.
Executing

Explanation: