During which of the following process groups is the preliminary project risk assessment
performed?
A.
Monitoring/Controlling
B.
Planning
C.
Initiating
D.
Executing
Explanation:
During which of the following process groups is the preliminary project risk assessment
performed?
During which of the following process groups is the preliminary project risk assessment
performed?
A.
Monitoring/Controlling
B.
Planning
C.
Initiating
D.
Executing
Explanation: