which of the following process groups is the availability of required resources for the project determined?

During which of the following process groups is the availability of required resources for the project
determined?

During which of the following process groups is the availability of required resources for the project
determined?

A.
Executing

B.
Monitoring/Controlling

C.
Initiating

D.
Planning

Explanation: