Which of the following describes the point in time when resources can be assigned to scheduled
tasks?
A.
When the project statement of work (SOW) has been created
B.
When the project deliverables have been defined
C.
When the work breakdown structure (WBS) is decomposed into work packages
D.
When the project WBS dictionary has been created
Explanation: