All of the following are part of the monitoring and controlling process group EXCEPT:
A.
updating the project charter.
B.
updating the project management plan.
C.
implementing change requests.
D.
updating the project scope.
Explanation:
All of the following are part of the monitoring and controlling process group EXCEPT:
All of the following are part of the monitoring and controlling process group EXCEPT:
A.
updating the project charter.
B.
updating the project management plan.
C.
implementing change requests.
D.
updating the project scope.