Which of the following tools would be the BEST to use?

A project manager is performing activity duration estimation. This project will have conditional
decisions. Which of the following tools would be the BEST to use?

A project manager is performing activity duration estimation. This project will have conditional
decisions. Which of the following tools would be the BEST to use?

A.
GERT

B.
Gantt chart

C.
PERT

D.
EVM

Explanation: