which of the following would the project manager use to assess the strengths and weaknesses of the project?

After final acceptance, which of the following would the project manager use to assess the
strengths and weaknesses of the project?

After final acceptance, which of the following would the project manager use to assess the
strengths and weaknesses of the project?

A.
Post-project review

B.
Transition plan

C.
Project kick-off meeting

D.
Quality analysis

Explanation: