The project manager crashes a project that is behind schedule and under-budget. Which of the
following will be the intended result?
A.
The project will be behind schedule and over-budget.
B.
The project will be on schedule but over-budget.
C.
The project will be on schedule and on-budget.
D.
The project will be behind schedule and on-budget.
Explanation: