Which of the following shows a project that is presently over its financial budget?
A.
CPI = 1.4
B.
CPI = 0
C.
CV = +$11,000
D.
CPI = 0.8
Explanation:
Which of the following shows a project that is presently over its financial budget?
Which of the following shows a project that is presently over its financial budget?
A.
CPI = 1.4
B.
CPI = 0
C.
CV = +$11,000
D.
CPI = 0.8
Explanation: