Which of the following steps should the project manager take to resolve the conflict?

Several team members have criticized the project manager for requesting that they work overtime
in order to complete a project on time. Which of the following steps should the project manager
take to resolve the conflict?

Several team members have criticized the project manager for requesting that they work overtime
in order to complete a project on time. Which of the following steps should the project manager
take to resolve the conflict?

A.
Force the team members to work and terminate any who do not comply.

B.
Avoid the conflict by asking the stakeholders to talk to the team members.

C.
Compromise and let the team members finish the project late.

D.
Discuss schedule options with team members.

Explanation: